Public Works Capital Projects
May 2019 Annual Town Meeting
Article | Group | Project Name | Appropriation ($) | Project Update |
---|---|---|---|---|
21 | Facilities | High School Tennis Courts | 668,000 | Complete - Reconstruction of the Tennis Courts was completed in November of 2020. |
22 | Facilities | Cedar School Security Improvements | 260,000 | Project has been bid and bids are currently being reviewed.
Installation of a security film treatment on the existing curtain wall was completed on August 2nd. |
23 | Facilities | Renovate Cedar School Bathrooms | Complete - Work has been completed. | |
26 | Highway | 4x4 Pickup Truck with Plow | 42,000 | Complete - Vehicle has been purchased an is in service. |
27 | Public Grounds | Cemetery One-ton Dump Truck | 70,000 | Complete - Vehicle has been purchased an is in service.. |
33 | Water Distribution | Water Service Van Replacement | 38,000 | Complete - Vehicle has been purchased an is in service. |
34 | Water Distribution | Water Mains 2020 | 300,000 | Approved by Town Meeting 5/6/2019. Developing final specification. |
May 2018 Annual Town Meeting
Article | Group | Project Name | Appropriation ($) | Project Update |
---|---|---|---|---|
20 | Highway | Large Dump Truck 19 | 190,000 | Complete - Vehicle has been purchased and is in service. |
21 | Water Distribution | One-ton Dump Truck Replacement | 63,000 | Complete - Vehicle has been purchased and is in service. |
23 | Public Grounds | One-ton Dump Truck 19 | 63,000 | Complete - The one ton dump truck has been purchased and equipped and is in service. |
24 | Water Treatment | Pond Street Generator Replacement | 200,000 | This project to replace a 45 year old generator for the Town's main water treatment plant is currently in design. The project includes a new generator and automatic transfer switch. We expect it will go to bid in the summer of 2019 with construction in the fall of 2019. |
25 | Water Distribution | Towed Air Compressor 19 | 25,000 | Complete - The towed air compressor has been purchased and equipped and is in service. |
27 | Water Distribution | Water Mains 2019 | 200,000 | Complete - Heavy Construction Work has been completed on this Phase of the Project.
This is the second phase of a project to reinforce fire flow capabilities for the large buildings in the center of town through the installation of a 12-inch reinforcing water main on Main Street from Plain Street to the center of town.
The May 2018 appropriation will continue the water main installation from Meeting Hill Lane to Grove Street. |
29 | Highway | Street Light Conversion | 190,000 | Complete - The conversion to LED street lights commenced in February of 2019 was completed in June of 2019. |
May 2017 Annual Town Meeting
Article | Project Name | Appropriation ($) | Project Update |
---|---|---|---|
33 | Large Dump Truck 18 | 190,000 | Complete - The large dump truck has been purchased and equipped and is in service |
24 | Pickup Truck with plow 18 | 41,000 | Complete - The pickup truck with plow truck has been purchased and equipped and is in service |
35 | Dam Repairs Design 18 | 30,000 | Repairs to the Curtis Crossing Dam are currently in design and are expected to take place in the summer of 2019 in conjunction with the Town of Pembroke if funds are appropriated at the May 2019 Annual Town Meeting |
36 | Broadway Media and Related Work 2018 | 80,000 | The work under this project is ongoing. Valves have been replaced on several filters which should reduce waste and improve reliability and water quality. Additional valve work is on-going. Media was tested and found to be in better condition than expected. As such, we expect to simply add media that has been lost through operations over the past few years rather than fully replacing all of the media. |
37 | 2.5 ton Vibratory Roller 18 | 40,000 | Complete - The vibratory roller has been purchased and equipped and is in service |
38 | Tractor 18 | 32,000 | Complete - The tractor for the cemetery has been purchased and equipped and is in service |
39 | Water Mains 2018 | 200,000 | This is the first phase of a project to reinforce fire flow capabilities for the large buildings in the center of town through the installation of a 12-inch reinforcing water main on Main Street from Plain Street to the center of town. The May 2017 appropriation funded installation of a 12-inch reinforcing main on Main Street from Plain Street to Meeting Hill Lane. Worked was performed by Town forces with the help of rented equipment. A leveling course of asphalt will be placed over the project area in the summer of 2019. The project will continue through the appropriation in Article 27 of the May 2018 Town Meeting in the summer of 2019. |
40 | Treatment Plant Upgrades | 2,800,000 | Work under this project is ongoing. The article provided funding for a number of projects at all three treatment plants. Some of this work such as replacement of chemical storage and chemical feed systems was included in the disinfection byproduct reduction work that is currently under construction. Control work is proceeding as is pump replacements. The projects contemplated under this article need to be carefully staged to not take treatment plants off-line and to not interfere with existing disinfection byproduct construction activities and as such we are waiting for disinfection byproduct work to be completed before taking on some of these projects. |
May 2016 Annual Town Meeting
Article | Project Name | Appropriation ($) | Project Status |
---|---|---|---|
STM-4 | Water Master Plan 2016 | 100,000 | This project was designed to update the hydraulic model of the water distribution system and to make recommendations for capital improvements. The first step in the project was to update the system map and hydraulic model. In updating the map, the department and its consulting engineers did a comprehensive review of available maps and historical files, expanding the original scope of the project, to ensure that the final map and model were as accurate as possible. This work has been completed. The engineers are awaiting guidance on the level of effort that the Town wants to employ to calibrate the hydraulic model. Fully calibrating the model will require extensive flow testing in the system to stress the system which will stir up sediments, causing townwide water quality issues. At this point the engineers are performing a desktop calibrating using standpipe levels, treatment flows, and user demand data. After this preliminary calibration is complete a final decision on full calibration will be made as well as the final goals of the master planning process. |
STM-5 | Pond Street Equipment 2016 | 500,000 | This project will make improvements to and replace equipment inside the settling tanks at the Pond Street Water Treatment Plant. The project has been designed and is currently under review by the Massachusetts Department of Environmental Protection (Mass DEP). Construction can only take place in the winter months as the Pond Street WTP will have to be off-line for extended periods to replaced the equipment. We expect the work will take place in the winter of 2019-2020. |
23 | Wood Chipper 17 | 40,000 | Complete - The wood chipper has been purchased and is in service. |
24 | Fuel Pumps 17 | 60,000 | New fuel pumps were installed in May of 2019. |
25 | Large Dump Truck 17 | 190,000 | Complete - The large dump truck has been purchased and equipped and is in service |
26 | Vacuum Sweeper 17 | 250,000 | Complete - The vacuum sweeper has been purchased and equipped and is in service |
27 | Crane Truck Replacement 2016 | 135,000 | Complete - Vehicle has been purchased and is in service. |
28 | Stormwater 17 | 80,000 | This project funded upgrades to the Town's stormwater management plan and Notice of Intent to comply with the 2018 General Permit of Municipal Separate Storm Sewers under the Federal Clean Water Act. |
29 | WTP Upgrades 2016 (THM) | 1,519,200 | This project will reduce disinfection byproducts in the water distribution system. The project has been designed, permitted, bid, and improvements are currently under construction at all three water treatment plants. Work was delayed as a result of design and permitting taking longer than originally anticipated. Currently, equipment has been approved and ordered, underground work at the Broadway treatment plant is largely complete, and temporary chemical feed systems have been installed and tested at all three treatment plants. With temporary systems in place, demolition has commenced on existing feed systems, and relocation of electrical control panels is in progress. While there is major work ahead of us, we expect the disinfection byproduct reduction work to come on-line in the fall of 2019. |
30 | Water Mains 2016 | 200,000 | Project is complete. A 12-inch ductile iron water main on Plain Street from Circuit Street to Hanover Street has been installed and is in service. The roadway was overlaid after the project was completed. |
Future Project Updates
From the tables above, we hope you can see that work is in progress on a number of projects and purchases. We are in the process of creating project specific web pages to better inform the public of this progress and invite you to check back often to view our progress.