2022 Roadway Resurfacing & Paving Work
Resurfacing/Paving Improvements
Main Street
- Approximate Limits of Work: Webster Street to Norwell Town Line
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Mid-Late July
Whiting Street
- Approximate Limits of Work: Virginia Road to Norwell Town Line
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
- Asphalt milling was completed on 06/28/22.
- A leveling course of asphalt was placed on 06/30/22.
Homestead Lane
- Approximate Limits of Work: Whiting Street to Bayberry Lane
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
- Asphalt milling was completed on 06/27/22.
- A leveling course of asphalt was placed on 06/29/22.
Old Schoolhouse Lane
- Approximate Limits of Work: Whiting Street to Anderson Farm Road
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
- Asphalt milling was completed on 06/27/22.
- A leveling course of asphalt was placed on 06/29/22.
Mill Brook Way
- Approximate Limits of Work: Whiting Street to Bayberry Lane
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
- Asphalt milling was completed on 06/27/22.
- A leveling course of asphalt was placed on 06/29/22.