Roadway Resurfacing & Paving Work

sign

Resurfacing/Paving Improvements

North Street

  • Cold Plane/Level/Overlay
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work.
  • Cold Planing/Grinding of the existing roadway surface was performed on Monday, August 5, 2019.
  • A leveling course of asphalt/pavement was placed on Tuesday, August 6, 2019
  • Raising and adjusting took place in early October.
  • A final course of asphalt/pavement was placed on October 22, 2019.

Main Street

  • Cold Plane/Level (Plain Street - Meeting Hill Lane) & Trench Restoration (Meeting Hill Lane - Grove Street)
    • This year's proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, & installing temporary pavement markings as needed.
  • Cold Planing/Grinding of the existing roadway surface was performed on Monday, August 5, 2019
  • A leveling course of asphalt/pavement was placed on Tuesday, August 6, 2019.

Bailey Road

  • Level/Overlay with Curbing & Sidewalk Improvements
    • Proposed work includes placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), adjusting existing curbing, installing new ADA compliant wheelchair ramps, sidewalk resurfacing/improvements, placing a new finish course of asphalt/pavement, & roadway shoulder restoration work.
  • A leveling course of asphalt/pavement was placed on Wednesday, August 7, 2019
  • Curbing adjustments began on September 19, 2019.
  • Raising and adjusting took place in early October.
  • A final course of asphalt/pavement was placed on October 21, 2019.

Tucker Road

  • Level/Overlay with Curbing & Sidewalk Improvements
    • Proposed work includes placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), installing new curbing & sidewalk (Cedar Street - Bailey Road), installing new ADA compliant wheelchair ramps, placing a new finish course of asphalt/pavement, & roadway shoulder restoration work.
  • A leveling course of asphalt/pavement was placed on Wednesday, August 7, 2019Curbing
  • Curbing adjustments began on September 19, 2019.
  • Raising and adjusting took place in early October.
  • A final course of asphalt/pavement was placed on October 21, 2019.

Aspen Drive

  • Level/Overlay with Curbing & Sidewalk Improvements
    • Proposed work includes placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), adjusting existing curbing, installing new ADA compliant wheelchair ramps, sidewalk resurfacing/improvements, placing a new finish course of asphalt/pavement, & roadway shoulder restoration work.
  • A leveling course of asphalt/pavement was placed on Wednesday, August 7, 2019
  • Curbing adjustments began on September 19, 2019.
  • Raising and adjusting took place in early October.
  • A final course of asphalt/pavement was placed on October 21, 2019.

Russell Road

  • Level/Overlay with Curbing & Sidewalk Improvements
    • Proposed work includes placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work.
  • A leveling course of asphalt/pavement was placed on Thursday, August 8, 2019
  • Raising and adjusting took place in early October.
  • A final course of asphalt/pavement was placed on October 22, 2019.

Crack Sealing

Various Streets

  • Work is preliminarily scheduled for the Spring of 2020

Handicap Accessible Sidewalk Ramps

  • Pleasant Street
  • Whiting Street
  • West Ave
  • Cedar Street
  • Silver Street