2023 Roadway Resurfacing & Paving Work

sign

Resurfacing/Paving Improvements

  • Old Farm Road

    • Approximate Limits of Work: Plain Street to 150' North of Fair Acres Drive
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Mid-May
  • Plain Street

    • Approximate Limits of Work: Plain Street to 150' North of Fair Acres Drive
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Mid-May
  • Anderson Farm Lane

    • Approximate Limits of Work: Old Schoolhouse Lane to Whiting Street
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Mid-May
  • Ann Marie Lane

    • Approximate Limits of Work: Route 139 to End.
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Late June/Early July
  • Old Cross Street

    • Approximate Limits of Work: Center Street to Cross Street
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Late June/Early July
  • Main Street

    • Approximate Limits of Work: Center Street to Grove Street
    • Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Late June/Early July
  • Mill Street

    • Approximate Limits of Work: Route 53 to Norwell Town Line
    • Proposed work includes raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
    • Work is scheduled to take place in Late June/Early July

 