2023 Roadway Resurfacing & Paving Work
Resurfacing/Paving Improvements
Old Farm Road
- Approximate Limits of Work: Plain Street to 150' North of Fair Acres Drive
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Mid-May
Plain Street
- Approximate Limits of Work: Plain Street to 150' North of Fair Acres Drive
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Mid-May
Anderson Farm Lane
- Approximate Limits of Work: Old Schoolhouse Lane to Whiting Street
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Mid-May
Ann Marie Lane
- Approximate Limits of Work: Route 139 to End.
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
Old Cross Street
- Approximate Limits of Work: Center Street to Cross Street
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
Main Street
- Approximate Limits of Work: Center Street to Grove Street
- Proposed work includes cold planing/grinding of the existing roadway surface, placing a new leveling course of asphalt/pavement, raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
Mill Street
- Approximate Limits of Work: Route 53 to Norwell Town Line
- Proposed work includes raising and adjusting all structures (manholes, basins, etc.), placing a new finish course of asphalt/pavement, installing new pavement markings, & roadway shoulder restoration work (as needed).
- Work is scheduled to take place in Late June/Early July
Attachment | Size |
---|---|