Road Work on Broadway Starting 6/8

Road work will start on Broadway 6/8/16 from Spring Street to the Hanson line.  It will consist of 2-4 days  of cold planing 2" followed up next week with a leveling course of asphalt. Upon completion of the leveling course T.L. Edwards will then start adjusting structures to finish grade in preparation for the final course of asphalt.  Hanover DPW is working with Hanover Police on the traffic patterns and will post any detours. There will be four detail officers each day for traffic control.  A message board will be placed at Broadway and Elm Street saying  "BROADWAY ROAD CONST. SEEK ALT ROUTE".